Cause & Consequence
- Failure of vessels or pipework
Incident Location
Fixed Installation
Incident Activity
Lifting, crane, rigging, deck operations
Specific Incident Equipment
During an ESD process shutdown, the Production Header PSV 10032 lifted
Lessons Identified
- Insufficient procedures had been developed over the operating life of the installation to cover this eventuality.
- There were human factors involved as not all operations personnel were fully aware of the full procedure for alignment prior to well start-up.
- Mechanical failure of the choke valve. In conjunction with the procedural and knowledge shortfall, a coincidental failure of the mechanical choke valve exacerbated the incident
Incident Recommendations
- An improved Wellheads/manifolds procedure has been developed to cover this shortfall.
-Additional training and knowledge sharing has been introduced to ensure better understanding of the alignment issues for well start-up.
-A revision to the Wellheads/manifold procedure to identify choke valve failure will be introduced.